Whittley
A 3.96Kw install with 18 Schott 220w Solar Panels and Sunny Boy 3800 Inverter. Installed in 4 days to budget.
Expected payback within 8 years. Expecting to generate around 3300 KW of electricity per year. Generating an annual income of around £1770 tax free from the feed in tariff and saved energy.
A TYPICAL SOLAR POWER INSTALLATION
A domestic solar power installation is typically done over one or two days and has several key elements, which are broken down below.
Survey
We check your home is in a suitable location and is structurally suitable for solar panels to be fitted.
Quotation
A detailed quotation is given.
Preparation
All the materials needed are assembled and a convenient time for installation is agreed
Roofing and Panel installation
Our expert roofing team prepare the roof and install the panels.
Electrical installation
Our team of experienced electricians will connect the panel to your houses electrical system, along with the inverter and the new meters
Testing
The system is fully tested and signed off, we will not finish the installation until you are 100% satisfied